Key Features of work scope
The project includes all infrastructure detailed below including 360,000 m² of Asphalt paving and 101,000 m² of concrete sidewalks.
- Site clearance
- Water Distribution System
- Earthworks
- Water Pumping Station
- Roads, including parking and fencing
- Reservoir
- Landscape/hardscape, including parking sheds
- Elevated Water Tank
- Guardhouse for water distribution
- Storm drainage system (36 KM)
- Sewage Treatment Plant
- Blended water system (25 KM)
- Sitework
- Irrigation system (3 KM)
- Blower building
- Sanitary sewer system (18KM)
- Operation & Maintenance building
- Road lighting Guardhouse (for the sewage treatment Plant)
- Electrical distribution system (60KM)
- Telecom distribution system (32 KM)